Implementation of Bozhou Haichuang 2×6M m2 Fiber Cement Board Production Line Project is now going on smoothly.

Blending station is mostly completed.

600m。2000 m rails have been finished.

Installation of main part of the boiler room has been ready. Embody of cables has been finished.

Inlet, outlet, reducer and motor of the mill has been finished.